彭博社:美国数据中心自建电厂规划约90GW,实际运行约2GW

AI 导读

彭博社称,美国数据中心开发商已宣布约90GW的自建电厂项目,但目前实际运行的只有约2GW,约占2%。自建电厂缺少电网的多线路备用能力,还要应对AI负载的快速波动;开发商因此多将其作为接入电网前的过渡方案。

原帖引用 · 原文

@rohanpaul_ai

https://t.co/g5O3IPaCnt

回复Rohan Paul@rohanpaul_ai
Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans: developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far. The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup. AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year. So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.
在 X 查看这条帖子 ↗

来源:Rohan Paul · x.com

行业
发现内容有误?提交纠错