彭博社:自备电源的数据中心(“表后供电”)目前大多仍停留在规划阶段:
开发商已宣布为美国数据中心建设约 90 吉瓦的自有发电设施(“表后供电”),但迄今实际投入运行的仅约 2 吉瓦,占比约 2%。
一台设备发生故障时,电网仍能持续供电,因为它可以依靠多个发电厂和输电线路,而单个现场发电厂没有这样的备用支持。
AI 工作负载也会在几秒内引起用电需求波动,幅度足以损坏一些现场发电机;如果采用太阳能加电池,要让得克萨斯州一座 100 兆瓦的数据中心在一年中仅有 98% 的时间正常运行,就需要将近 1,800 公顷土地。
因此,开发商建设额外的燃气发电能力,支付每兆瓦时超过 100 美元的电力成本,而电网供电约为每兆瓦时 90 美元;他们大多将自有发电厂视为电网接入前的过渡方案。
Original
Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans: developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far. The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup. AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year. So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.