Bloomberg: About 2GW of planned 90GW of US data center power plants is operatingMachine translation

AI introduction

Bloomberg reports that developers have announced about 90GW of their own power plants for US data centers, but only about 2GW, or around 2%, is operating. On-site plants lack the grid’s backup from multiple plants and lines and must handle rapid swings in AI demand; developers mostly use them as a bridge until a grid connection arrives.

Original post · AI translation

@rohanpaul_ai
Translation · refer to the original

https://t.co/g5O3IPaCnt

ReplyRohan Paul@rohanpaul_ai
Translation
彭博社:自备电源的数据中心(“表后供电”)目前大多仍停留在规划阶段: 开发商已宣布为美国数据中心建设约 90 吉瓦的自有发电设施(“表后供电”),但迄今实际投入运行的仅约 2 吉瓦,占比约 2%。 一台设备发生故障时,电网仍能持续供电,因为它可以依靠多个发电厂和输电线路,而单个现场发电厂没有这样的备用支持。 AI 工作负载也会在几秒内引起用电需求波动,幅度足以损坏一些现场发电机;如果采用太阳能加电池,要让得克萨斯州一座 100 兆瓦的数据中心在一年中仅有 98% 的时间正常运行,就需要将近 1,800 公顷土地。 因此,开发商建设额外的燃气发电能力,支付每兆瓦时超过 100 美元的电力成本,而电网供电约为每兆瓦时 90 美元;他们大多将自有发电厂视为电网接入前的过渡方案。
Original

Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans: developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far. The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup. AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year. So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.