Anthropic 正在洽谈租赁埃德蒙顿附近的一处超大规模数据中心园区,该园区将由一座专用的 920 兆瓦燃气发电厂供电。
总部位于卡尔加里的 Beacon Data Centers 正在开发斯特金县的这处场址;其申报文件显示,该场址将设有 4 座用于人工智能计算的数据机房。
艾伯塔省公用事业委员会于 10 月 23 日批准了这座发电厂,计划于本季度开工,并于 2027 年末投入运营。
这将使该园区的供电能力达到新斯科舍省一处 420 兆瓦场址的约 2 倍;Anthropic 已为后者签订了为期 20 年的租约。
原文
Anthropic is negotiating to lease a hyperscale data centre campus near Edmonton powered by a dedicated 920MW gas plant. Calgary-based Beacon Data Centers is developing the Sturgeon County site, which its filings show will hold 4 data halls for AI computing. Alberta’s Utilities Commission approved that plant on October 23, with construction due this quarter and service in late 2027. That would give the campus about double the power of the 420MW Nova Scotia site, where Anthropic signed a 20-year lease.