OpenAI plans power cutbacks at Georgia data center during grid demand peaksMachine translation

AI introduction

OpenAI says Georgia Power can cut up to 1,000MW of power to its planned Effingham County data center during demand peaks. The company estimates that power could meet the average demand of about 700,000 households; even at the maximum cutback, the campus would still draw about 2,200MW.

Original post · AI translation

@rohanpaul_ai
Translation · refer to the original

OpenAI表示,其未来的数据中心将在当地电网过载时减少用电,首先从佐治亚州开始。

这项名为“Grid Protectors”的计划推出之际,当地反对数据中心的声音正在增加。

根据首份协议,在热浪等用电需求高峰期,佐治亚电力公司可将OpenAI计划中的埃芬汉县园区的用电量削减最多1,000兆瓦。

这些电力随后可供家庭使用。据该公司估算,足以满足约700,000户家庭的平均用电需求。

即使削减额度用足,该数据中心仍会消耗约2,200兆瓦电力,因为削减的只是其约3,200兆瓦需求中的1,000兆瓦。

OpenAI认为,一个用电量大且稳定的客户能让其他人受益,因为电力线路的固定成本可以分摊到更多电力销售量上。

Source: Rohan Paul · x.com