Rohan Paul· @rohanpaul_ai · X· · 原发布时间 AI 评分53

美国数据中心自建电厂规划约90吉瓦,实际运行约2吉瓦

AI 导读

彭博社称,美国数据中心开发商已宣布约90吉瓦自建电厂计划,但目前实际运行的仅约2吉瓦。自建电厂缺少电网的多重备用电源,还要应对AI负载快速波动;开发商因此增建燃气发电能力,并将自有电厂主要用作接入电网前的过渡方案。

原帖引用 · 原文

@rohanpaul_ai

Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans:

developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far.

The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup. AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year.

So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.

来源:Rohan Paul · x.com