TrendForce: Top-end GPU lead times rise to 45 weeks as Rubin transition beginsMachine translation

AI introduction

TrendForce says top-end GPU lead times rose by five weeks to 45 weeks. Hyperscalers will likely receive NVIDIA’s Rubin first, while enterprise buyers remain on existing GPU platforms. DRAM lead times eased by one week to 19 weeks but remain more than twice normal; substrates and capacitors, with lead times more than three times balanced levels, also constrain Rubin’s ramp.

Original post · Original

The article text is unavailable in this language; an existing version is shown.

@rohanpaul_ai

TrendForce: Top-end GPU lead times jumped 5 weeks to 45 as NVIDIA’s Rubin transition begins.

Hyperscalers will likely get NVIDIA’s Rubin first, leaving enterprise buyers on existing GPU platforms.

96GB and 128GB RDIMMs are arriving faster, but 32GB and 64GB modules remain severely tight.

DRAM lead times eased 1 week to 19, yet still run more than double normal.

Since a server ships only when its slowest part arrives, Rubin’s ramp depends on substrates and capacitors running more than 3 times their balanced lead times.

Source: Rohan Paul · x.com